Tiling underway, Alucobond underway, kitchen partially replaced 2/12/2013



Not much action the last week but today a little more action to report on site

Tiling has commenced. Tiler reported today he found a few boxes of tiles that had damaged edges and bowed during manufacturing. When we told him how much $$$ we paid extra to national tiles for these Argentinian porcelain tiles he said he would try and have them replaced. Meeting with Site superior tomorrow so will let him know the issue. 
He is a good tiler and a nice young man, they have good trades at CG. 


Kitchen has been replaced partially today, old kitchen removed and new cabinet shells have been installed. Pot drawers and cupboards are now equal widths and we have pot drawers on island bench instead of cabinet doors. Doors and drawers should be in by Xmas. 



Alucobond has also been about 80% installed. It has finished off the facade nicely can't wait to see render finished and Alucobond unwrapped!