Tiler finish (about 95%done)
Electrical fit off (mostly done but a few errors with putting in double GPOs instead of the quads we had in plans, power points missed and ensuite 3 GPO on wrong side of bench - all rectifiable)
Render completed to alfresco (50% done)
Downpipes installed and plumbed( not done)
Site cleanup and temp fence removed (not done)
Drawers and cabinet drawers installed in kitchen (not done)
Island bench stone completed (half done)
Garage roller door (not done)
Aircon and heating vents installed (not done)
On a positive note all our side and rear fences are done and are looking good.
Merry Christmas!